A Mixed-Integer Linear Programming Approach for Multi-Stage Security-Constrained Transmission Expansion Planning
By Hui Zhang, Vijay Vittal, Gerald Thomas Heydt, J. Quintero. IEEE Transactions on Power Systems, 2012
263 citations recorded by the source corpus.
Subfields: Electrical and Electronic Engineering, Safety, Risk, Reliability and Quality
View Paper: https://www.semanticscholar.org/paper/37a3bf5a6dcca2c3654b80703bc0ab6b38635875
How researchers see this paper
The researchers whose trusted networks rank it highest, strongest advocate first. Every researcher gets a different order.
In Electrical and Electronic Engineering
- Marcos J. Rider
- Mohsen Rahmani
- Rubén R. Romero
- Kevin Tomsovic
- Xiaohu Zhang
- Aleksandar D. Dimitrovski
- Chongqing Kang
- Qing Xia
In Safety, Risk, Reliability and Quality
- Marcos J. Rider
- Junhua Zhao
- Zhao Yang Dong
- Chongqing Kang
- Qing Xia
- Kit Po Wong
- Rubén R. Romero
- Kevin Tomsovic
Citations in the corpus
- Multi-Stage Flexible Expansion Co-Planning Under Uncertainties in a Combined Electricity and Gas Market (2015, background): “al, 2012 [86] linear programming approach that considers generator costs, transmission losses and the N-1 security constraints for multi-stage transmission expansion problems.”
- A Linearized OPF Model With Reactive Power and Voltage Magnitude: A Pathway to Improve the MW-Only DC OPF (2018, methodology): “An improved linearized network model based on the Taylor series expansion is used for the OPF problem in [25], [26].”
- Security Constrained Multi-Stage Transmission Expansion Planning Considering a Continuously Variable Series Reactor (2017, background): “Checking N − 1 security constraints iteratively is an effective way to reduce the computational burden in the TEP problem [3], [30].”
- Strategies to Reduce the Number of Variables and the Combinatorial Search Space of the Multistage Transmission Expansion Planning Problem (2013, background): “The N-1/N-2 contingencies [24], the uncertainty of future scenarios [25], the environmental impacts [26] and market considerations [27] can all change the constraints or objectives of the planning: among them, the N-1 security is one of the most important issues in transmission planning that has bee”